Buyer guide

How is the technical offer evaluated in Saudi government tenders on Etimad, and when is the financial offer opened?

Where the tender documents require a technical offer separate from the financial offer (two electronic files), technical offers are opened and examined first, on their own, against the criteria in the tender documents. An unacceptable technical offer is excluded and its financial offer is returned unopened with the bid bond. The committee then examines the financial offers of the accepted technical offers only and recommends the best one (Articles 43 and 44 of the Government Tenders and Procurement Law). In practice: if the technical offer fails, the price is never looked at.

Updated 12 Oct 2026 · sources checked 12 Oct 2026

Numbers every bidder should know

RuleArticle
Offers are submitted encrypted through the portal, within the set period only36
Offers stay valid for 90 working days from bid opening; a bidder who withdraws in that time loses the bid bond39
Total prices go in the offer itself; a discount in a separate letter is ignored; prices can't change after submission except where negotiation is allowed40
Bid bond of 1% to 2% of the offer value; no bond, no acceptance41
Local SMEs are exempt from the bid bond, but pay a 2% fine where a bond would have been forfeited42
A low bid can only be excluded if it is 25% or more below the estimated cost, after the bidder is asked in writing to explain it46
Standstill of 3 to 10 working days after award before the contract is signed, so bidders can object50

Worked example: a live Etimad tender

On 12 Oct 2026 we read the public page of tender 260639010130 (كاساو/2026/009): five-year operation and maintenance of a wastewater treatment plant for King Saud bin Abdulaziz University for Health Sciences. This is what a visitor sees without logging in, and how it maps to the articles above:

Listing fieldValueWhat it means
Submission methodTwo separate files (technical and financial)Technical offers are examined first; a rejected technical offer's price is never opened (Article 44)
Bid bondRequired1% to 2% of the offer value; local SMEs are exempt (Articles 41 and 42)
Final guarantee5%Posted after award
Tender documents feeSAR 1,500The booklet must be bought before the offer is prepared
Submission deadline / opening8 Nov 2026, 09:59 / 9 Nov 2026, 10:00No offer is accepted after the period (Article 36)
Standstill period5 daysWithin the 3 to 10 working days of Article 50
Local contentMinimum local content mechanism, 70% targetThe bid must state its targeted local content percentage

The 8 evaluation criteria, 27 bill-of-quantities lines and 21 attachments only show after registering and buying the booklet. That is why we build the compliance matrix from the booklet itself, not from the listing page.

How to prepare a technical offer that passes

  1. Extract every requirement in the booklet; mark it mandatory or scored, with its weight under the published evaluation criteria.
  2. Map each requirement to where your offer answers it and the evidence that proves it, in one compliance matrix.
  3. Answer the mandatory items first: an offer that doesn't comply with the tender documents is excluded (Article 44(1)).
  4. Keep every price out of the technical file in a two-file tender; prices belong in the financial offer.
  5. Check the statutory documents and bid bond before the deadline; late offers are not accepted (Article 36(2)).

The law's official text is in Arabic; article numbers refer to the current Government Tenders and Procurement Law as published by the Ministry of Finance.

Common questions

When is the financial offer opened in a Saudi government tender?

After the technical offers are examined, and only for accepted technical offers. A bidder whose technical offer is rejected gets the financial offer back unopened, with the bid bond (Article 44).

Can I change my price after submitting the bid?

No, except in the cases where the law allows negotiation. A discount offered in a separate letter is not counted, even if attached to the offer (Article 40).

Are SMEs exempt from the bid bond?

Yes. Article 42 exempts local SMEs from the bid bond, but they must pay a fine of 2% of the offer value in cases where the bond would have been forfeited.

How long does a bid stay valid?

90 working days from the bid-opening date. The government entity may extend it if the bidder agrees and extends the bond (Article 39).

Next step

Mutabiq prepares the Arabic technical envelope within 72 hours of complete inputs, with a compliance matrix mapping every booklet requirement to where it is answered and the evidence. You sign and submit on Etimad.

Request a free compliance matrixSee Mutabiq

Official sources

  1. نظام المنافسات والمشتريات الحكومية، الباب الثالث: العروض والترسية (وزارة المالية)
  2. نظام المنافسات والمشتريات الحكومية (هيئة الخبراء بمجلس الوزراء)
  3. Etimad tender 260639010130 (كاساو/2026/009), public visitor listing as mirrored by sauditenders.co, read 12 Oct 2026

How this guide was made: drafted with AI assistance from the official sources listed at the end, then every number, date and article reference was checked against those sources on the date shown above.